Challenging Inadequate Environmental Review of Vantage's Port Washington Data Center

MEA filed a lawsuit against the Wisconsin Department of Natural Resources on behalf of the Sierra Club over the agency’s decision to issue permits for a massive data center campus in Port Washington without fully evaluating the project’s environmental consequences. A settlement in the case requires the DNR to conduct a comprehensive statewide review of the environmental impacts of data center development, including demands on water and energy resources, impacts on air quality and climate, and the effects of related infrastructure such as power plants and transmission lines.

State Regulators Fail to Conduct Required Environmental Review

On July 10, 2026, Midwest Environmental Advocates filed a lawsuit on behalf of the Sierra Club challenging a Wisconsin Department of Natural Resources (DNR) decision to issue permits for a massive data center campus in Port Washington without fully evaluating the project’s environmental consequences.

The lawsuit was filed after emails obtained through a public records request revealed that DNR staff initially informed data center representatives that a detailed Environmental Impact Statement (EIS) would be required due to the scope and scale of the project. After data center representatives complained that an EIS would “kill the project,” the DNR reversed course and decided to conduct a more limited “environmental analysis summary.”

A Project of Unprecedented Scale

The Port Washington data center is unlike anything Wisconsin has seen before. It will completely transform the local landscape, consume staggering amounts of electricity and water and significantly increase fossil fuel emissions.

Vantage Data Centers, Oracle, and OpenAI are building the project as part of a broader effort to expand computing infrastructure for artificial intelligence. It is one of the first hyperscale data centers under construction in Wisconsin. The first phase alone will require an unprecedented 1.3 gigawatts of power—an amount that could power more than half a million households. The data center itself will cover 672 acres, and its energy demand will spur the construction of new gas plants, substations and high-voltage transmission lines that will spread over six counties.

The Need for Full Environmental Review

In comments submitted to the DNR earlier this year, MEA and the Sierra Club urged the DNR to prepare a comprehensive Environmental Impact Statement that would evaluate the data center’s direct, indirect, and cumulative environmental impacts. In particular, they pointed to the inconsistency and lack of transparency regarding the infrastructure needed to support the data center’s extraordinary energy demands.

While the project’s public-facing website and other marketing materials tout renewable energy development, they make little or no mention of the new fossil fuel infrastructure—including the new Foundry Ridge gas plant in Walworth County—that will be built to power the Port Washington data center. 

When data center developers aren’t forthright with the public and regulators aren’t willing to hold them accountable, it’s difficult to understand the true environmental impact of a single project, much less the combined impact of multiple hyperscale data centers. 

A Successful Settlement

A settlement in the case was finalized on October 16. The settlement requires the DNR to prepare a statewide, comprehensive environmental review of data center development in Wisconsin. The statewide review makes Wisconsin one of the few states taking a comprehensive look at the environmental impacts of data center development.

Settlement terms include:

  • By January 2028, the DNR must complete a statewide strategic analysis–a process that will examine the broader environmental consequences of data center development, including demands on water and energy resources, impacts on air quality and climate, and the effects of related infrastructure such as power plants and transmission lines.
  • Vantage Data Centers must pay all costs related to the strategic analysis.
  • The DNR must provide opportunities for public engagement and input as part of the strategic analysis process.

MEA Attorney Michael Greif

 

our Current climate & Energy work

LEGAL ACTION

Securing the Constitutional Rights of Wisconsin Youth to a Stable Climate

MEA and Our Children’s Trust are representing fifteen young people from Wisconsin who filed a groundbreaking climate lawsuit against the Wisconsin Legislature and the Public Service Commission for enacting and enforcing unconstitutional laws that exacerbate the climate crisis.

LEARN MORE →

LEGAL ACTION

Preventing New Construction on Enbridge’s Line 5 Pipeline

Midwest Environmental Advocates is taking legal action to stop Enbridge Energy from moving forward with a plan to build a new 41-mile segment of its Line 5 oil pipeline in northern Wisconsin.

LEGAL ACTION

Demanding Data Center Transparency – City of Racine

MEA filed a legal action on behalf of Milwaukee Riverkeeper to enforce the Public Records Law when the City of Racine failed to respond to a request seeking information about projected water use at Microsoft’s massive Mount Pleasant data center.

LEARN MORE →

LEGAL VICTORY!

Demanding Data Center Transparency in Beaver Dam

MEA took legal action after the Public Service Commission denied our public records request seeking information about projected energy demand for Meta’s Beaver Dam data center. The PSC claimed the information was a trade secret and that withholding it served the public interest. A Dane County circuit court disagreed, finding that the agency had acted unlawfully and ordering that the information be released.

LEARN MORE →

POLICY & ADVOCACY

Taking Action to Improve Air Quality in Beloit

With legal support from MEA, members of the Stateline Clean Air Coalition are raising the alarm over harmful levels of air pollution in the Beloit and speaking out against the expansion of a gas-fired power plant along the Wisconsin-Illinois border.

LEARN MORE →

POLICY & ADVOCACY

Advocating for Sustainable Alternatives to the Expansion Of I-94

Wisconsin transportation officials are proposing a controversial $1.1 billion dollar expansion of I-94 in Milwaukee. MEA is advocating for a more just and sustainable alternative that prioritizes the health and wellbeing of people living adjacent to the corridor. 

LEARN MORE →

latest news

Climate & Energy Updates

Legal settlement leads to statewide environmental review of data center development in Wisconsin

A legal settlement secured by MEA on behalf of Sierra Club requires the Wisconsin Department of Natural Resources to conduct a comprehensive statewide review of the environmental impacts of data center development. The settlement resolves a lawsuit challenging the DNR’s decision to issue permits for the Vantage data center campus in Port Washington without preparing a full Environmental Impact Statement.

Read More »

Wisconsin youth ask state supreme court to take up constitutional climate case

Fifteen youth plaintiffs represented by MEA and Our Children’s Trust filed a petition asking the Wisconsin Supreme Court to take up Dunn v. Wisconsin Public Service Commission directly, bypassing the Court of Appeals. Their case raises urgent questions of state constitutional law that are too important to wait years for resolution in the lower courts, all while the state continues to approve new fossil fuel infrastructure that exacerbates climate change

Read More »

Legal victory! Judge orders release of information about energy use at Meta’s Beaver Dam data center

This week, a Dane County Circuit Court sided with MEA in a dispute over the public’s right to know how the unprecedented energy needs of hyperscale data centers will impact Wisconsin. The court ruled that the Public Service Commission acted unlawfully when it denied a public records request seeking information about energy use at Meta’s Beaver Dam data center and ordered that the information be released.

Read More »