MEA is taking legal action to stop Enbridge Energy from building a new 41-mile segment of its Line 5 oil pipeline in northern Wisconsin. Details about how and when that litigation will unfold came into focus this week when Administrative Law Judge Angela Chaput Foy issued a scheduling order for the contested case hearing, which is set to begin in August.
What is a contested case hearing?
A contested case hearing is similar to a court trial and is conducted by the Division of Hearings and Appeals. A hearing examiner, also known as an administrative law judge, runs the hearing much like a judge runs a trial. The parties can make opening statements, present evidence, call witnesses and make closing arguments.
What is at issue in this case?
Permits and other regulatory approvals issued by the DNR are being challenged. They include:
- a wetland fill and waterway crossing permit
- a decision to convey coverage under the department’s General Permit for Construction Site Storm Water Discharge
- a determination that the project will meet State of Wisconsin water quality standards.
Who is challenging the permits?
- Midwest Environmental Advocates (on behalf of Sierra Club, the League of Women Voters of Wisconsin and 350 Wisconsin)
- Clean Wisconsin
- Bad River Band of Lake Superior Chippewa
When and where will the contested case hearing take place?
- Aug 12 in Ashland
Opening statements & public testimony - Sept 3 in Madison
Public testimony - Sept 4 – 12 in Madison
MEA (on behalf of Sierra Club, 350 Wisconsin and League of Women Voters of Wisconsin) and Clean Wisconsin present their case - Sept 15 – 19 in Ashland
Bad River Band of Lake Superior Chippewa present their case - Sept 22 – 26 in Madison
Enbridge presents its case - Sept 29 – Oct 3 in Madison
DNR presents its case
Can members of the public participate?
Yes.
Observing the hearing
Members of the public may observe the hearing in person. The hearing will also be available by video and telephone.
Public testimony
Public testimony may be given in person on August 12 in Superior and on September 3 in Madison. Members of the public who choose to testify are open to cross-examination by Enbridge attorneys.
Learn more about our Line 5 work here.